Recent Projects

Kemsley Paper Mill - K4 CHP Plant

Combined Heat and Power Plant comprising a gas turbine (57 MW), Waste Heat Recovery Boilers (105MWsteam) and Steam Turbine (80MW)

Based on approx. 350 auger piles.

Piling has started October 2019 and because of Covid-19 delays the plant has started on Nov 2021 .

Wares Farm Packing Facilities for "FIRMIN"  Linton

It is a hall with an area of 15,000 square meters.

The office part is located on the mezzanine floor of 5000 square meters.

A part of the hall is a cold store about 30%.

The entire building is supported by approximately 170 columns.

The first earthworks started in December 2018

and a year later the building has worked for "BerryGardens".

Kemsley Paper Mill - AD Project BioGas Plant

Biogas is obtained from the water used in the mill's processes.

The project is based on auger piling under siloes and the driven piles under the rest of structures.

The works has started in August 2017

Beaurepaire House - Bramley Phase 1

This structure is "stuck" to existing 16th century listed building.

The steel frame building is seated on 10 meter of depth basement.

The basements has approx. 1500 m sq and is build by secant piling wall. The seal of the basement was the biggest challenge because the estate is surrounding by moat. 


The works has started in August 2015